Students waited two years for their new school. Fire safety requirements were clarified too late

This article has been translated to English using AI.

Atuarfik Inussuk was due to welcome students in August 2024. But when the school year was about to begin, the municipality could not sign off on fire safety. An independent review by Rambøll found that clearer requirements from the outset could have made the construction process simpler.

Students were due to start at Atuarfik Inussuk in Nuuk on 15 August 2024. Two months earlier, the municipality’s external fire safety adviser, COWI, had raised serious concerns about the school’s fire safety strategy. The design-build contractor, Ístak, disputed that the project had shortcomings. The municipality was unable to issue an occupancy permit, and the school did not welcome students until 17 August 2026.

Commissioned by Kommuneqarfik Sermersooq, Rambøll reviewed the project from the tender in 2019 to the handover in October 2025. The review identifies several factors that affected the schedule, including unresolved fire safety requirements, travel restrictions and difficulties getting construction materials delivered.

Two building codes made the requirements harder to clarify

The project had to take both the Greenlandic and Danish building codes into account. Under the tender terms, the Greenlandic code took precedence wherever it imposed stricter requirements. Rambøll found that clearer wording in the tender could have made it easier to determine which requirements applied.

Questions about fire curtains and smoke ventilation remained under discussion through several stages of the project. Rambøll suggests that bringing in an independent, certified fire safety adviser early could help resolve such questions sooner on future projects.

The pandemic also put pressure on the schedule

The initial master schedule called for handover in March 2023. Shortly after construction began in 2020, Ístak warned that travel restrictions were making it harder to bring specialist workers to Greenland. The pandemic also disrupted deliveries. Rising prices and shortages of materials later put further pressure on the project.

When the building was handed over on 25 October 2025, significant shortcomings remained, according to the report. These included issues with fire-stopping and the testing of technical systems. The client and Ístak agreed on how the shortcomings would be addressed and how the outstanding work would be paid for.

The construction contract came to nearly DKK 639 million

The original contract with Ístak was worth just over DKK 614 million. Rambøll puts the value of the design-build contract at nearly DKK 639 million after additions. The figure covers the construction contract. The municipality’s total investment and the sprinkler system later commissioned for the entire development fall outside the scope of the report’s assessment.

Around 1,080 students began attending classes in the new building when Atuarfik Inussuk opened in August 2026. The school was officially inaugurated on 1 October.

  • Invitation: Kittat 45 år

    Kittat skin-sewing workshop turns 45 and launches website on Greenlandic national dress

  • Local ingredients to give tourists more food experiences in Tasiilaq

  • PIKIALAARFIK is off and running: A week of culture and creativity for children and young people